Chip seal work by the Cass County Highway Department is underway. Over the next few weeks, drivers may encounter roads where chip seal work is underway. In most cases, the roads will remain open to traffic but drivers may encounter delays, and are encouraged to take alternate routes if possible while the work is going on. Following the chip seal, drivers should be alert for loose stone. Residents may notice some dust on roadways for a few weeks after the chip seal work is done.
Roads scheduled for chip seal on Thursday 8/25, or the next dry weather day, include:
Center Street in Lincoln
700E from US 35 to SR 18
Completion of these roads will complete the chip seal phase of the regular locally funded road program for this year. Any projects funded by the Community Crossings Grant will be completed either later this fall or next spring/summer.
Roads tentatively scheduled for chip seal on Wednesday 8/24 include:
Pottawatomie Pt. Road
Longtree Lane
700E from US 35 to SR 18
Walnut Street in Lincoln
Drivers should prepare for delays while the work is going on, and take an alternate route if possible.
Roads tentatively scheduled for chip seal on Tuesday 8/23 include:
450S from 175W to 250W
400W from Old 25 to just west of overpass
375W from 300S to 225S
400S from 500W to 600W
325S from 600W to 675W
275W from 200S to 225S
Here are the roads tentatively scheduled for chip seal on Monday 8/22, weather permitting:
800E from 325S to 500S
400E from 500S to SR 218
900S from US 35 to 700E
1050S from US 35 to 800E
350S from SR 29 to 175W
Roads scheduled for chip seal work Friday 8/19, weather permitting, include:
1000S between 700E and US 35
800E between 325S and 500S
400E between 500S and SR 218
900S between 700E and US 35
1050S between 800E and US 35
Roads tentatively scheduled for chip seal work on Thursday 8/18 include:
1150S from 800E to 950E
950E from 1150S to US 35
1050S from US 35 to 800E
900S from 700E to US 35
800E from 325S to 500S
1000S from 700E to US 35
Rain has postponed the planned chip seal work for Monday 8/15. Work on the scheduled roads (below) will be planned for Tuesday or the next dry weather day:
1175S between 400 and 500E
1250S from 150E to 300E
1300S from 300E to 400E
400E from SR 18 to 1400S
900S from 700E to US 35
1050S from 800E to US 35
1150S from 800E to 950E
950E from 1150S to US 35
Roads tentatively scheduled for chip seal work on Friday 8/12 include the following:
600E from 600S to 900S
950S from Carroll County line to 100E
1250S from 150E to 300E
1300S from 300E to 400E
400E from 1100S to 1175S
400E from SR 18 to 1400S
1100S from 400E to 500E
Roads which are tentatively scheduled for chip seal work on Thursday, Aug. 11 include the following:
475E from 250S to 300S
350S from 325E to 425E
500S from SR 29 to 50E
600S from 200E to 300E
750S from 400E to 500E
950S from the Cass/Carroll line to 100E
Roads tentatively scheduled for chip seal on Wednesday, Aug. 10 include the following:
Division Road at 1100E
1025E from Logansport Road to dead end
1000E from Logansport Rd to US 24
1075E from Logansport Rd to Lewisburg Rd
Lewisburg Rd from 900E to 1000E
450S from 850E to 950E
550S from 800E to 850E
600S from 850E to 900E
850E from 550S to 600S
Roads tentatively scheduled for chip seal on Tuesday, Aug. 9, 2016 include the following:
325N between 275E & 400E
300N between 50E & St Rd 25
225N between 450E & 500E
800E between 150N & Logan Rd
1000E between 100N & Division Rd
1075E between Logan Rd & Lewisburg Rd
Lewisburg Rd between 900E & 1000E
Roads tentatively scheduled for chip seal on Monday, Aug. 8, 2016 include the following:
500N between 600E & 700E
550N between 900E & 1100E
600E between 900E & 1000E
300E between 375N & 475N
Here are the roads tentatively scheduled for chip seal work on Friday, Aug. 5.
325E between 900N & 1000N
900N between 900E & 1000E
800N between 700E & 800E
700E between St Rd 16 & 625N
600E between 800N St Rd 17
Here are the roads that are tentatively scheduled for chip seal work on Thursday, Aug. 4.
Delaware Rd. between 150N & Holland St.
75N between St Rd 25 & 100N
350E between 150N & 300E
300N between 50E & St Rd 25
Here are roads that are tentatively scheduled for chip seal work on Wednesday, Aug. 3. Crews will likely start with roads at the top of the list and work down. Any roads which to not get done on their scheduled day would be scheduled for the following day.
200N from US 35 to 400W
150N from US 35 to 400W
Delaware Road/350W from US 35 to 150N
600W from 50N to 100N
Work started August 1 in Boone Township. Each day’s schedule will depend upon weather and circumstances that arise. Roads that could see chip seal August 1 include:
1050W from 800N to 900N
900N from 925W to US 35
Royal Center Pike from 1000N to US 35
300W from 900N to 1000N
375W from Royal Center Pike to 400N
300N from 600N to 400N
SOURCE: News release from Cass County Highway Department
Chip seal schedule for Tuesday 8/2
Roads which could see chip-seal work on Tuesday include:
300W from 400N to 600N
375W from Royal Center Pike to 600N
100W from SR 16 to 800N
200N from 350W to 450W
150N from US 35 to 400W