advertisers

2022 chip seal schedule updates from Cass County Highway Department

Last Updated on June 29, 2022 by Cass County Highway Department

Chip seal work started Monday, June 6, 2022 in Cass County with roads in Jefferson and Boone Township being treated.


Roads scheduled for chip seal on Wednesday 6/29 include:

700W from 400S to 500S

275W from 200S to River Road

Wednesday’s work will conclude chip seal application for this year’s season. Roads to be paved will be announced as that work begins.


 Roads tentatively scheduled for chip seal on Tuesday 6/28 include:

1300S from Carroll County Line to 50E

1150S from Carroll County Line to 50E

1250S from 150E to 200E

100E from 950S to 1050S

600E from SR 218 to 800S

600S from 900E to 950E

Any roads not finished on the assigned day will be moved to a subsequent day.

Drivers may encounter temporary road closures while the chip seal work, which is a rolling operation, is completed.


Roads tentatively scheduled for chip seal work on Monday 6/27 include:

1000S from 300E to 500E (partially done, to be completed)

300E from 1000S to 1100S (partially done, to be completed)

400E from 1000S to 1175S

300E from 1350S to SR 18

1250S from 150E to 200E

125E from SR 18 to 100E

1300S from 25E to 100E

1150S from County line to 50E

100E from 950S to 1050S

Any roads not finished on the assigned day will be moved to a subsequent day.

Drivers may encounter temporary road closures while the chip seal work, which is a rolling operation, is completed.


Roads tentatively scheduled for chip seal work on Thursday 6/23 include:

1000E from 700S to 950S (to be finished)

1100E from 1100S to 1300S

1300S from 1025E to 1100E

300E from 1350S to SR 18

1250S from 150E to 200E

125E from SR 18 to 100E

1300S from 25E to 100E

1150S from County line to 50E

100E from 950S to 1050S

300E from 1000S to 1100S

Drivers may encounter temporary road closures while the chip seal work, which is a rolling operation, is completed.

Any roads not completed on the announced day will be moved to the next work day.


Roads tentatively scheduled for chip seal on Wednesday, June 22 include:

700E from US 24 to 250S

1100E from 500S to 700S

700S from 1000E to 1100E

1000E from 700S to 950S

800S from 1000E to 1100E


Roads tentatively scheduled for chip seal work Tuesday, June 21 include:

100N from 700E to 900E

50N from 800E to 950E

800E from Logansport Road to Division Rd

South River Road (150S) from 500E to 600E


Roads which are tentatively scheduled for chip seal work on Monday 6/20 include:

450N from 925E to 1100E

525E from 150N to 225N

550E/100N from 150N to 525E

525E/75N from 100N to 450E

100N from 700E to 900E


    Roads tentatively scheduled for chip seal work on Thursday 6/16 include the following:

500E from 525N to SR 16 (to be completed)

1000E from SR 16 to 900N

600N from 1050E to 1100E

450N from 925E to 1100E


The following roads are tentatively scheduled for chip seal work on Wednesday 6/15:

850N from 200E to 250E

650N from 175E to SR 25

475N from SR 25 to 300E

375N from 300E to 400E

500E from 525N to SR 16


Due to an equipment breakdown, Tuesday’s chip seal list looks similar to Monday’s. Roads tentatively scheduled for chip seal work Tuesday 6/14 include:

50E from 350N to 500N (partially done, to be finished Tuesday)

500N from 100E to SR 25

100E from 600N to 1000N

650N from 175E to SR 25


Chip seal work tentatively scheduled for Monday, June 13, 2022 includes :

200N between Royal Center Pike and SR 17

50E from 350N to 500N

500N from 100E to SR 25

100E from 600N to 1000N

650N from 175E to SR 25


Roads scheduled for work Wednesday, June 8 include the following:

525W from 900N to 1000N

400W from SR 16 to 800N

350W from Sr 16 to 800N

275W from 800N to 900N

    Chip seal is a rolling operation so any road closures or delays should generally be brief in nature. Drivers are encouraged to take an alternate route if possible while work is underway.

SOURCE: News release from Cass County Highway Department

Cass County Online