Here is more info on a NIPSCO project underway as of February 2023:

Cass, Howard and Miami County
The purpose of this project is to provide natural gas service to the StarPlus Energy, joint venture, battery plant in Kokomo. Installation: 18.5 miles of new 24″ natural gas steel pipeline & 1500′ of 16″ steel pipeline, a new station facility north of Walton to include new valve settings and safety components, a new customer facility station in Kokomo.

Fact Sheet (PDF; graphics below)

Project Fusion Fact Sheet